Monday, May 25, 2015

Sathyabama University Specification and Estimation May2014

Register Number







                               
SATHYABAMA UNIVERSITY
(Established under section 3 of UGC Act,1956)

Course & Branch :B.Arch - ARCH
Title of the Paper :Specification and Estimation   Max. Marks:80
Sub. Code :SARX1008(2010/2011/2012)              Time : 3 Hours
Date :03/05/2014                                                    Session :FN
___________________________________________________________________________________________________________________________

(Sketch wherever necessary)                                            

PART – A                       (8 x 4 = 32)
Answer All the Questions
1.     What is meant by Tender documents?

2.     What are the types/methods of calling for tender?

3.     Discuss the format of a Detail estimate.

4.     Mention the general rules for measuring any interior work.

5.     Explain the procedure adopted for rate analysis.

6.     What is depreciation?  Explain various methods of evaluating depreciation.

7.     What do you mean by
        (a) Obsolescence            (b) Annuity

8.     What is a specification of work?

PART – B                       (4 x 12 = 48)
Answer All the Questions

9.     Explain Plinth area estimate and cube rate estimate in detail.
(or)
10.   What are the duties and responsibilities of a client and a contractor in the execution of a project? Discuss in detail.

11.   A Shed has been constructed for Rs. 15,000 assuming salvage value at the end of 6 years as Rs. 3,000.  Determine the amount of depreciation and book value for each year by sinking fund method.
(or)
12.   Discuss the role of various financial agencies for building and land development. 

13.   Estimate the quantity of materials required for the following items of work for a building shown in figure 1.
        (a) R.C.C. in beams, slabs and column (from G.L. onwards) assume beam thickness 30cms.
        (b) Painting.
(or)
14.   Estimate the quantity of materials required for the following items of work for a building shown in figure 1.
        (a) Brick work in super structure (G.L. onwards)
        (b) Plastering (internal)

15.   Give short notes on
        (a) Methods determining depreciation
        (b) Valuation of building       
(or)
16.   Describe the following terms in valuation    
        (a) Gross income                    (b) Net income
        (c) Scrap value                        (d) Salvage value
Figure I
Share This
Previous Post
Next Post

B.E Civil Engineer Graduated from Government College of Engineering Tirunelveli in the year 2016. She has developed this website for the welfare of students community not only for students under Anna University Chennai, but for all universities located in India. That's why her website is named as www.IndianUniversityQuestionPapers.com . If you don't find any study materials that you are looking for, you may intimate her through contact page of this website to know her so that it will be useful for providing them as early as possible. You can also share your own study materials and it can be published in this website after verification and reviewing. Thank you!

0 comments:

Pen down your valuable important comments below

Search Everything Here