Do you want 152505 Project Management V Semester B.E GTU Question Paper asked in previous years ? You can here download of the paper appeared in Summer 2015 examinations conducted by Gujarat Technological University. Go through the contents added below.
GTU Question Paper
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER–V EXAMINATION
SUMMER 2015
Subject Code: 152505
Date: 15/05/2015
Subject Name: Project Management
Time: 02.30 pm-05.00 pm
Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Q.1 (a) Define project. Classify the project and explain in brief. 07
(b) What do you understand by phases of project management? 07
Q.2 (a) Write a short note on work break down structure. 07
(b) What is project overview statement (POS)? Explain its parts. 07
OR
(b) Explain the requirement of joint project planning session to develop POS. 07
Q.3 (a) Write a short note on resource requirement. 07
(b) Explain estimation of project with respect to activity duration. 07
OR
Q.3 (a) Describe resource leveling and its importance. 07
(b) Explain the format of work package with reference to its purpose. 07
Q.4 (a) Explain the rule to draw a network diagram by plotting a network of your choice. 07
(b) Differentiate between CPM and PERT. 07
OR
Q.4 (a) Define critical path, ES, EF, LS, LF, dummy activity and slack. 07
(b) Write a brief note on resource allocation. 07
Q.5 (a) Describe crashing of project network. 07
(b) Elaborate different time estimates in PERT. 07
OR
Q.5 (a) What is joint project planning? Which facilities are to be considered for the purpose? 07
(b) Make a project proposal of manufacturing a 100 passenger vessel. 07
GTU Question Paper
Seat No.: ________ Enrolment No.___________
GUJARAT TECHNOLOGICAL UNIVERSITY
BE - SEMESTER–V EXAMINATION
SUMMER 2015
Subject Code: 152505
Date: 15/05/2015
Subject Name: Project Management
Time: 02.30 pm-05.00 pm
Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Q.1 (a) Define project. Classify the project and explain in brief. 07
(b) What do you understand by phases of project management? 07
Q.2 (a) Write a short note on work break down structure. 07
(b) What is project overview statement (POS)? Explain its parts. 07
OR
(b) Explain the requirement of joint project planning session to develop POS. 07
Q.3 (a) Write a short note on resource requirement. 07
(b) Explain estimation of project with respect to activity duration. 07
OR
Q.3 (a) Describe resource leveling and its importance. 07
(b) Explain the format of work package with reference to its purpose. 07
Q.4 (a) Explain the rule to draw a network diagram by plotting a network of your choice. 07
(b) Differentiate between CPM and PERT. 07
OR
Q.4 (a) Define critical path, ES, EF, LS, LF, dummy activity and slack. 07
(b) Write a brief note on resource allocation. 07
Q.5 (a) Describe crashing of project network. 07
(b) Elaborate different time estimates in PERT. 07
OR
Q.5 (a) What is joint project planning? Which facilities are to be considered for the purpose? 07
(b) Make a project proposal of manufacturing a 100 passenger vessel. 07