University Of Pune Question Paper
M.C.A. (Management Faculty) (Semester – V) Examination, 2010
IT 52 : SOFTWARE IT PROJECT MANAGEMENT
(2008 Pattern)
Time : 3 Hours Max. Marks : 70
Note: 1) Q. 1 and Q. 8 are compulsory.
2) Solve any 5 from Q. 2 to Q. 7.
1. a) You are required to give cost estimation for the project of size 32,000 LOC. 6
b) Define CPM/PERT. 4
2. Why change control is necessary ? Explain structured change control
process. 1 0
3. What is maintainability ? Discuss various maintainability metrices. 10
4. “Testing is crucial phase in Project” Comment. 10
5. a) Explain IT infrastructure management. 5
b) How FPA is useful for cost estimation ? 5
6. What do you mean by a project ? How S/W projects are unique in the
characteristics ? 10
7. “User is very important in Project Management” Comment. 10
8. Write short note on (any two) : 10
i) Items of S/W configuration Management.
ii) Tools for S/W Project Management.
iii) Activities in SQA.
iv) Acceptance testing.
————————
M.C.A. (Management Faculty) (Semester – V) Examination, 2010
IT 52 : SOFTWARE IT PROJECT MANAGEMENT
(2008 Pattern)
Time : 3 Hours Max. Marks : 70
Note: 1) Q. 1 and Q. 8 are compulsory.
2) Solve any 5 from Q. 2 to Q. 7.
1. a) You are required to give cost estimation for the project of size 32,000 LOC. 6
b) Define CPM/PERT. 4
2. Why change control is necessary ? Explain structured change control
process. 1 0
3. What is maintainability ? Discuss various maintainability metrices. 10
4. “Testing is crucial phase in Project” Comment. 10
5. a) Explain IT infrastructure management. 5
b) How FPA is useful for cost estimation ? 5
6. What do you mean by a project ? How S/W projects are unique in the
characteristics ? 10
7. “User is very important in Project Management” Comment. 10
8. Write short note on (any two) : 10
i) Items of S/W configuration Management.
ii) Tools for S/W Project Management.
iii) Activities in SQA.
iv) Acceptance testing.
————————