University Of Pune Question Paper
M. C. M. (Semester - III) Examination - 2010
SOFTWARE PROJECT MANAGEMENT AND IT MANAGEMENT
(New 2008 Pattern)
Time : 3 Hours] [Max. Marks : 70
Instructions :
(1) Question No. 1 is compulsory.
(2) Attempt any five from the remaining.
(3) Neat diagrams carry marks.
(4) State assumptions made, if any.
(5) Question 1 carries 20 marks. Remaining questions carry 10
marks each.
Q.1) (A) Listed in the table are the activities and sequencing necessary
for a maintenance job on the heat exchangers in a refinery :
Activity Description Predecessor
Activity
A Dismantle Pipe Connection –
B Dismantle Heater, Closure and
Floating Front A
C Remove Tube Bundle B
D Clean Bolts B
E Clean Heater and Floating Head Front B
F Clean Tube Bundle C
G Clean Shell C
H Replace Tube Bundle F, G
I Prepare Shell Pressure Test D, E, H
J Prepare Tube Pressure Test and
Reassemble I
Draw a network diagram for the project. [05]
(B) Explain COCOMO Model in depth with all its models and
example. [15]
Q.2) Describe various Software Project Time Estimation Tools, with suitable
illustration. [10]
Q.3) Explain in detail Function Point Analysis. [10]
Q.4) Explain different Software Testing Methods. Compare Black Box and
White Box Testing Methods. [10]
Q.5) Explain CMM in all its phases with example. [10]
Q.6) Explain in depth the Concept of Software Configuration Management. [10]
Q.7) Write short notes : (Any Two) [10]
(a) Software Maintenance
(b) Software Reviews
(c) Risk Management
(d) Soft Acquisition Procedure
M. C. M. (Semester - III) Examination - 2010
SOFTWARE PROJECT MANAGEMENT AND IT MANAGEMENT
(New 2008 Pattern)
Time : 3 Hours] [Max. Marks : 70
Instructions :
(1) Question No. 1 is compulsory.
(2) Attempt any five from the remaining.
(3) Neat diagrams carry marks.
(4) State assumptions made, if any.
(5) Question 1 carries 20 marks. Remaining questions carry 10
marks each.
Q.1) (A) Listed in the table are the activities and sequencing necessary
for a maintenance job on the heat exchangers in a refinery :
Activity Description Predecessor
Activity
A Dismantle Pipe Connection –
B Dismantle Heater, Closure and
Floating Front A
C Remove Tube Bundle B
D Clean Bolts B
E Clean Heater and Floating Head Front B
F Clean Tube Bundle C
G Clean Shell C
H Replace Tube Bundle F, G
I Prepare Shell Pressure Test D, E, H
J Prepare Tube Pressure Test and
Reassemble I
Draw a network diagram for the project. [05]
(B) Explain COCOMO Model in depth with all its models and
example. [15]
Q.2) Describe various Software Project Time Estimation Tools, with suitable
illustration. [10]
Q.3) Explain in detail Function Point Analysis. [10]
Q.4) Explain different Software Testing Methods. Compare Black Box and
White Box Testing Methods. [10]
Q.5) Explain CMM in all its phases with example. [10]
Q.6) Explain in depth the Concept of Software Configuration Management. [10]
Q.7) Write short notes : (Any Two) [10]
(a) Software Maintenance
(b) Software Reviews
(c) Risk Management
(d) Soft Acquisition Procedure