University Of Pune Question Paper
M.C.A. (Sem. – V) (Management Faculty) Examination, 2010
BM – 51 : SOFTWARE PROJECT MANAGEMENT
(2005 Pattern) (Old)
Time : 3 Hours Max. Marks : 70
Note : 1) Que. 1 and Que. 8 are compulsory.
2) Assume suitable data if required.
3) Solve any five from Que. 2 to Que. 7.
1. a) Explain the reasons for project failure. 5
b) Draw network diagram for the following project activities. 10
Activity Predecessor Duration (Days)
A – 2
B A 3
C – 3
D C 2
E D, J 3
F E, B 2
G F 2
H – 4
J H 2
i) Find critical path.
ii) If activity D takes 5 days, what is impact on project schedule.
2. What do you mean by “Resource Planning” and explain different types of resource
used in S/W project. 8
3. Write objective of Formal Technical Review and what it includes. 8
4. What do you mean by repository and explain its role in software configuration
management. 8
[3880] – 54
5. What are different software quality standard ? Explain in detail SEI-CMM and its
significance with the software industry. 8
6. Explain recruitment process of IT personnel. 8
7. Explain different types of testing and what its role in project. 8
8. Write short note on (any 3) : 15
a) User role in Project Management
b) Team Models
c) Change Control
d) MS-Project.
————————
B
M.C.A. (Sem. – V) (Management Faculty) Examination, 2010
BM – 51 : SOFTWARE PROJECT MANAGEMENT
(2005 Pattern) (Old)
Time : 3 Hours Max. Marks : 70
Note : 1) Que. 1 and Que. 8 are compulsory.
2) Assume suitable data if required.
3) Solve any five from Que. 2 to Que. 7.
1. a) Explain the reasons for project failure. 5
b) Draw network diagram for the following project activities. 10
Activity Predecessor Duration (Days)
A – 2
B A 3
C – 3
D C 2
E D, J 3
F E, B 2
G F 2
H – 4
J H 2
i) Find critical path.
ii) If activity D takes 5 days, what is impact on project schedule.
2. What do you mean by “Resource Planning” and explain different types of resource
used in S/W project. 8
3. Write objective of Formal Technical Review and what it includes. 8
4. What do you mean by repository and explain its role in software configuration
management. 8
[3880] – 54
5. What are different software quality standard ? Explain in detail SEI-CMM and its
significance with the software industry. 8
6. Explain recruitment process of IT personnel. 8
7. Explain different types of testing and what its role in project. 8
8. Write short note on (any 3) : 15
a) User role in Project Management
b) Team Models
c) Change Control
d) MS-Project.
————————