Dr.A.P.J.Abdul Kalam University
Master of Business Administration
Third Semester Main Examination, Dec-2020
Project Management [MBA302C]
Time: 3:00 Max Marks 80
Note : Attempt any five questions.
All question carry equal marks.
Q.1 How does cost to change and possibility of value addition vary during project life cycle?
Q.2 What is Appropriate Technique? What factors make technology in appropriate?
Q.3 Discuss the social cost and benefits considered during Social cost benefit analysis.
Q.4 Discuss in detail any two models of Quantitative and Non-quantitative used for project
selection with the suitable examples.
Q.5 What is Technical analysis and how would you evaluate appropriateness of a technology.
Q.6 Discuss the procedure for determining whether a project should be continued, terminated
or divested.
Q.7 How is Project Monitoring undertaken? Explain project termination and audit.
Attachment & Scanned Copies:
0 comments:
Pen down your valuable important comments below